For descriptions and maps of the projects, see Projects.

Project Schedule

West Tenino Pedestrian Path

October 1, 2015

October 2015 through November 2015

Kot-Num Pedestrian Path

December 1, 2015

December 2015 through February 2016

Webster Flat Fiber Extension

February 1, 2016

February 2016 through March 2016

Upper Dry Creek Realignment

April 1, 2016

April 2016 through June 2016

M300 Culvert Replacement

June 1, 2016

June 2016 through August 2016

East Spur Resurfacing

August 1, 2016

August 2016 through September 2016

West Spur Resurfacing

October 1, 2016

October 2016 through November 2016